John Fernely School, Phases 1 & 2
Location:
Melton Mowbray
Completed:
September 2011
Subcontract value:
£150k
Client:
Willmott Dixon
Systems:
PermaRock 30mm Mineral Fibre Insulated Render System
Finishes:
1.5mm Silicone Render
Finish
Notes: Repex were initially appointed to carry out the first phase of the works
to John Fernely School. Once this phase was completed Willmott Dixon
invited Repex to tender for the second stage, Repex were once again appointed
to complete the (second stage) works and were delighted to continue on site.